Fastly 2021: a valid customer configuration triggers a latent bug
Real incident. Key points: progressive deployment.
Short answer
Real incident. Key points: progressive deployment. On June 8, 2021, Fastly published a summary of a global outage that occurred the same day. The post is the source for this case. According to the company, a previously undiscovered software bug surfaced when it was triggered by a valid customer configuration change.
01 · CONTEXT
A valid configuration and a bug nobody had seen
On June 8, 2021, Fastly published a summary of a global outage that occurred the same day. The post is the source for this case. According to the company, a previously undiscovered software bug surfaced when it was triggered by a valid customer configuration change.
Um CDN is a shared edge network, positioned between users and customers' sites. This case shows what it means to split the same layer among many customers.
02 · THE TRIGGER
A May deployment and a June configuration
On May 12, Fastly began a software deployment that introduced a bug. The bug could be triggered by a specific customer configuration under specific circumstances. Early on June 8, a customer pushed a valid configuration change that included those circumstances, and 85% of the network began returning errors.
On May 12, Fastly began a software deployment that introduced a bug.
Early on June 8, a customer pushed a valid configuration change.
That change included the specific circumstances that triggered the bug.
The network returned errors across 85% of its footprint.
The outage hit Fastly's customers and the people who depend on them.
03 · THE RESPONSE
From the first minute to the permanent fix
According to Fastly, the outage was detectada within a minute; then the cause was identified and isolated and the configuration was disabled. Within 49 minutes, 95% of the network was operating normally.
| Time (UTC) | Evento |
|---|---|
| 09:47 | Global outage begins |
| 09:48 | Outage identified by Fastly's monitoring |
| 09:58 | Status post published |
| 10:27 | Fastly engineering identifies the customer configuration |
| 10:36 | Affected services begin to recover |
| 11:00 | Most services recovered |
| 12:35 | Incident mitigated |
| 12:44 | Status post resolved |
| 17:25 | Bug fix deployment begins |
At 09:48 UTC, Fastly's monitoring identified the global outage.
At 10:27 UTC, Fastly engineering identified the customer configuration.
The cause was isolated and the configuration was disabled.
At 10:36 UTC, affected services began to recover.
At 12:35 UTC, the incident was considered mitigated.
At 17:25 UTC, the bug fix deployment began.
04 · COMMITMENTS
What the post promises to do
In its conclusion, Fastly states that, although the conditions that triggered the outage were specific, the company should have anticipated it.
| Stated commitment | |
|---|---|
| Bug fix | Deploy the fix to the network as quickly and as safely as possible |
| Post-mortem | Conduct a full post-mortem of the processes and practices followed in the incident |
| Testing and quality | Find out why the bug was not detected during the quality assurance and software testing processes |
| Remediation | Evaluate ways to improve remediation time |
| Plataforma | Make full use of the isolation capabilities of WebAssembly and Compute@Edge to build more resilience from the ground up |
05 · LESSONS
Questions for your design
This case invites us to look at disponibilidade in terms of blast radius: how much of the system can a single change reach?
It also invites us to look at the operations routine: how quickly does monitoring notice a problem, how quickly does the team find the trigger, and what does it take to disable it?
Frequently asked questions
What is Fastly 2021: a valid customer configuration triggers a latent bug?
Real incident. Key points: progressive deployment.
What does the Fastly 2021: a valid customer configuration triggers a latent bug design cover?
It is organized in these sections: A valid configuration and a bug nobody had seen, A May deployment and a June configuration, From the first minute to the permanent fix, What the post promises to do, and Questions for your design.
How long is Fastly 2021: a valid customer configuration triggers a latent bug and what level is it?
It takes about 12 minutes to read and is rated Mid level.